Total Project Budget = $1,481,200
What is Included:
•Kerns Group Architects
–Sean Reilly
•Chamberlain GCs
–Scott Houston
•Project Management from both companies
•Construction Timeframe 6 + 2 Months: 6 mths construction completion, 2 mths project completion
•Built in Contingency
–Design: 10%
–Construction: 10%
–Reimbursable Expenses: 5%
•Repro/ Copies/ Currier/ Travel
–Engineering & Architect Fees: 5%
What is not Included:
•Cost Escalation based on world events
•A 5% predicted rise in material pricing as of March
•Tokyo and Mid East = Unknown
•As long as fuel costs continue to escalate everything else follows, as if nothing else a good excuse to charge more
•The following have already gone up
•Drywall, insulation and metal studs.
•Stone and gravel
•Concrete has recently added a per yard fuel surcharge
•On the Horizon: All petroleum products
•Removed from Scope:
•Limited Landscaping
•Wood Narthex Ceiling
•Re-staining of Sanctuary Ceiling
•Reduction of AV Equipment Cost
•Removed Heated Floor
•Removed Acoustic Quality Glass